Commercial | Patented
Epoxy Barrier Coating

|
|


|
Memorial City Plaza
|
Houston, TX
The Problem:
The office building was suffering from failing
galvanized pipes that restricted water flow,
expelled rust-colored water and were engrossed
with pinhole leaks due to extensive corrosion
throughout the system. The building was 100%
occupied and a complete plumbing repipe was
not feasible.
|
|


|
Juneau
Centennial Hall |
Juneau, AK
The Problem:
The Juneau Centennial Hall is the largest convention center in Juneau,
the state capital of Alaska. Originally constructed in 1982 this
relatively new facility was experiencing signs of deterioration
of its copper piping system. Conventional repairs had been carried
to the piping system but the thought and expense of repiping the
entire facility was not a favorable option facing the management
of the convention center.
|
|


|
One
California Plaza
|
Los Angeles, CA
The Problem:
Early into the life of this world class facility the property engineers
noticed that they were having leaks in the water supply lines servicing
the building. In July 2000, an engineering report was commissioned
which helped in part to identify the extent of the damage to the
piping system.
|
|


|
Heights Medical Tower
|
Houston, TX
The Problem:
The main natural gas supply line from the City meter
to the building’s basement area was showing signs of
internal corrosion, a common problem with natural gas
supply lines. Using traditional pipe replacement
techniques would have meant that the patient drop-off
and parking areas would have been placed out of
service and worse yet would have been cut up to
install a new gas line. |
| |
|



|
City
of Houston Police Department |
Houston, TX
The Problem:
A run of approximately 220 linear feet of natural gas line running
beneath the driveway to the maintenance garage was isolated. The
pipe was a 2-inch, iron pipe gas line that ran directly between
the fuel center, Municipal Courts building, HPD parking facility
and motor pool garage at the Houston Police Department’s main
headquarters.
|



|
Lead
Solder |
WY and TX
The Problem:
The poison is lead. Lead leaching from pipes, lead solder and plumbing
fixtures into the water you drink, cook, bathe in and even brush
your teeth with. Drinking water for over 40 million Americans contains
lead in amounts exceeding EPA guidelines.
|



|
Seattle
King County Courthouse |
Seattle, WA
The Problem:
To protect and extend the life of the 4” main water line in
the Seattle Courthouse and main Administration building. The present
piping system was encrusted and wrapped in asbestos. Repair or replacement
had to be completed during 1 weekend as shut down of the facility
was not feasible.
|
| |
|


|
Glendale
Adventist Medical Center |
Glendale, CA
The Problem:
The problem was related to pipe corrosion in the piping system in
the Outpatient and Administrative Building’s chilled water
and heating system. The heating system had an operating temperature
of about 180° F.
|
|


|
Desert
Regional Medical Cntr |
Palm Springs, CA
The Problem:
The problem they were experiencing was related to pipe corrosion
in the piping system in the facilities chilled water and heating
system. The two pipe heating- cooling system was made of Schedule
40 black steel main lines with soft copper branch lines. |
| |
|
| |