Apartments|   Patented Epoxy Barrier Coating

 

 



Stoneybrook Condominiums  |  Sarasota, FL


The Problem:
The condominium complex was less than 10 years old yet the copper plumbing system was experiencing extensive pinhole leaks throughout the building’s plumbing system.

 

 

 



The Village Green  |  Los Angeles, CA


The Problem:
By 2001, the residents association realized that they had to do something to repair or replace the original galvanized piping system that serviced the entire project. Resident owner complaints, of the on-going failures, of the piping system included low flow, brown water, bad tasting water, pinhole leaks and pipe bursts.

 

 


The Webster House  |  Washington, DC


The Problem:
Built in the late 1960’s this 200 unit residential project was experiencing pinhole leaks in its copper water supply system. Upon investigation it was found that the failure of the copper piping systems was widespread throughout the project. The failure was effecting both hot and cold water lines. No single area of piping was immune to the effects of the pin holing.

 

 



Valley Palms  |  San Jose, CA


The Problem:
With a major overall upgrade slated for this income producing property, the owner was faced with a real dilemma. Part of the overall upgrade program included provisions to repipe the buildings. To repipe the buildings would mean massive tenant disruption, loss of income and extraordinary reconstruction costs.

 

 



Sunrise Calusa Harbor  |  Fort Myers, FL


The Problem:
The domestic water supply in the region is highly corrosive to copper piping, and by the late 1990’s had resulted in significant erosion and pinhole leakage throughout the copper system. Management was faced with the prospect of complete system replacement, and all of the challenges related to relocating an elderly and sensitive population around the building while such a project would be completed.